Ministry of Energy of the Kyrgyz Republic: The implementation of the Papanskaya Hydroelectric Power Station construction project continues

Евгения Комарова Exclusive
VK X OK WhatsApp Telegram
The author of the material is K-News. Any copying or partial use is possible with the permission of the K-News editorial office.

The Ministry of Energy of Kyrgyzstan reports that OJSC "Chakan HPP" continues active work on the construction project of the Papanskaya HPP.

Currently, the construction of temporary access roads extending for 9.2 km is underway, and the creation of a town for builders is nearing completion.

In addition, work is being done on the design and allocation of land plots for the creation of a 110 kV overhead power line, and the necessary permitting documents are being prepared, including approvals for blasting works that will be required for the construction of the diversion tunnel.

A preliminary environmental impact assessment (EIA) has also been developed for participation in the Green Energy Fund competition, which led to the signing of a lease agreement for the land plot for the construction of the HPP.

This project contributes to increasing generating capacities and enhancing the reliability of electricity supply in the southern regions of Kyrgyzstan.

Record from the Ministry of Energy of the KR: The implementation of the Papanskaya HPP construction project continues, first appeared in K-News.