How is the construction of the China - Kyrgyzstan - Uzbekistan railway progressing?

Юлия Воробьева Exclusive
VK X OK WhatsApp Telegram
At a meeting with representatives of the company implementing the project, Minister of Water Resources, Agriculture, and Processing Industry Erlis Akunbekov discussed the current stages of railway construction. This information was provided by the press service of the government.

Also participating in the discussion were leaders from the Ministry of Transport and Communications, as well as representatives from the national company "Kyrgyz Temir Zholu" and the railway company "China - Kyrgyzstan - Uzbekistan".

How the construction of the China - Kyrgyzstan - Uzbekistan railway is progressing


Photo from the website of the Cabinet of Ministers of the Kyrgyz Republic.



Photo from the website of the Cabinet of Ministers of the Kyrgyz Republic.



Photo from the website of the Cabinet of Ministers of the Kyrgyz Republic.

As of March 26, all major project materials are already ready, and currently, the drawings are being refined and coordinated with the relevant authorities. Active work is underway at the construction sites: more than 5,600 units of equipment and 5,000 workers have been engaged. The main focus is on tunnel excavation, earthworks, and bridge construction. To date, over 3.5 million cubic meters of earthworks have been completed.

The photo on the main page is illustrative: akchabar.kg.