Papanskaya Hydroelectric Power Station. At what stage is the construction, as reported by the Ministry of Energy

Наталья Маркова Local news / Exclusive
VK X OK WhatsApp Telegram
Papan Hydroelectric Power Station. The current stage of construction was reported by the Ministry of Energy




In the Kara-Suu district of the Osh region, the construction of the small hydroelectric power station "Papan," designed for a capacity of 27 MW, is actively underway.

According to information from the Ministry of Energy, several key stages of work have been completed to date:

Additionally, project and estimate documentation is currently being developed, a preliminary construction plan has been drawn up, permits for access to the Papan reservoir area have been obtained, and engineering surveys are ongoing.

It should be noted that the ceremonial laying of the capsule for the Papan HPP took place on October 5, 2024.
VK X OK WhatsApp Telegram

Read also:

World Nomad Games 2014

World Nomad Games 2014

The album features photographs by Vlad Ushakov, Sergey Ershov, Tөlөgön Amatov, Nurzhamal...

Electric Power Industry

Electric Power Industry

Before 1917, the electric power industry in Kyrgyzstan, as a separate branch of industry, hardly...

Papańskoe Reservoir

Papańskoe Reservoir

Reservoir in the Valley of the Ak-Bura River The location of the Papan irrigation reservoir basin...

Chatkal Ridge

Chatkal Ridge

Chatkal Ridge of the Central Tien Shan The mountain range in the Western Tien Shan, which limits...

Water Management

Water Management

In the system of water use and water consumption, intra-economic and inter-state water relations,...