In the Bakai-Ata District, overhead power lines will be repaired

Яна Орехова Local news / Exclusive
VK X OK WhatsApp Telegram

In the Talas region, in the Bakai-Ata district, a major overhaul of the overhead power lines with a total length of 29.985 km and a voltage of 10 kV is planned, as reported by the Ministry of Energy of the Kyrgyz Republic.

In addition, technical maintenance will be carried out on the following facilities:



As part of this program, the following works are also planned in the district:



In the village of Ken-Aral, as part of the reconstruction, 4.5 km of overhead line will be replaced with SIP-3 and 92 poles will be updated. In the village of Kyrgyzstan, the construction of 100 meters of 10 kV overhead line using SIP-3 and the installation of 6 new poles is also planned.