He noted that the following activities are planned for capital repairs in 2026:
- Capital repair of channels — 53 kilometers
- Concrete surface laying — 20.09 kilometers
- Channel concreting — 12.4 kilometers
- Mechanical cleaning of channels — 20.8 kilometers
- Capital repair of hydraulic structures — 22 units
- Capital repair of water measurement posts — 145 units
- Installation of water measurement sensors — 500 units
Additionally, the current repair plan includes the following works:
- Repair of channels — 170.5 kilometers
- Mechanical cleaning of channels — 81 kilometers
- Repair of water measurement posts — 516 units
- Repair of hydraulic structures — 579 units
- “Zhyltir” pumping station — 1 unit
Furthermore, Omuraliyev emphasized that funding in the amount of 21 billion soms has been allocated for the preparation of intra-farm irrigation networks for the 2026 growing season in the region.
Within this budget, the following works are planned for intra-farm irrigation networks:
- Repair of channels — 61 kilometers
- Mechanical cleaning of channels — 528 kilometers
- Manual cleaning of channels — 740 kilometers
- Repair of water measurement posts — 2 units
- Repair of hydraulic structures — 917 units