As of March 12, the old metal railings and asphalt have been completely dismantled from both sides of the bridge. Currently, new reinforced concrete beams have been installed, and the work on the bridge expansion is actively continuing.



Also, on the section of the road to Jibek Jolu Avenue (from 0 to 360 m), work on relocating power and communication lines, as well as earthworks, is ongoing.
It should be noted that due to the bridge expansion, the section of the Lebedinovka - HPP-5 highway (from 0 to 360 m) has been temporarily closed to traffic since February 15. It is planned that traffic will be restored by April 20.
The length of the Lebedinovka - HPP-5 highway is 5.1 km. As part of the current reconstruction, a change in the road category is planned, as well as an expansion from 2 to 4 lanes. The project includes street lighting, the construction of sidewalks on both sides of the large bridge, and a separate bridge for pedestrians. The work began in April 2025.