The audit found that the capital construction management of Bishkek increased the volume of construction by 13.5 million soms in 2023.

Евгения Комарова Local news
VK X OK WhatsApp Telegram
An audit conducted by the Accounts Chamber revealed that in 2023, the Capital Construction Department of Bishkek increased the volume of completed work on capital construction and repairs by 13 million 557.9 thousand soms. This information is contained in the budget report of the Bishkek City Hall for the current year.
The report specifies the concrete increases in the volume of work for the following projects:

- The construction of a recreation park on Ashar Street in the Ak-Örgö residential area, carried out by the contractor OsOO "DorStroyGroup," increased by 9 million 242.3 thousand soms.
- The contractor OsOO "Alliance Project" increased the volume of work on the construction of a sewage system in the Chalbay residential area by 257.6 thousand soms.
- The construction of the main sewage station on Japarov Street in the Kölmö residential area, carried out by the contractor OsOO "Ashar," increased by 637.8 thousand soms.
- The work on the construction of a sewage system on Budyonny Street from Jibek Jolu Street to the Chon Chuy Canal, also performed by OsOO "Ashar," increased by 893.9 thousand soms.
- The contractor OsOO "Ak-Niyet Kurułush" increased the volume of work on the construction of a preschool institution on Sadyr-Ake and Karkyra Streets in the Ak-Ordo residential area by 243.7 thousand soms.
- The construction of a power transmission line (10 kV from PS35/10) in the Kut residential area, carried out by ZAO "Bishkekelektro," increased by 129.6 thousand soms.
- OsOO "Hyper Stroy" increased the volume of work on the construction of an extension to kindergarten No. 26 on Samoylenko Street by 658.6 thousand soms.
- The contractor OsOO "Argyn Kurułush" increased the construction volume of a sports complex on the territory of school-gymnasium No. 68 on Toktogul Street by 192.1 thousand soms.
- The work on the construction of a bath and wellness complex on Jibek Jolu Avenue, performed by OsOO "Hyper Stroy," increased by 1 million 302.3 thousand soms.

In light of the above, the Capital Construction Department received the following recommendations:

- The contractor OsOO "Alliance Project" needs to redo work amounting to 257.6 thousand soms on the construction of the sewage system in the Chalbay residential area.
- The budget should recover 13 million 300.3 thousand soms for the increased volumes of work on the other listed projects.