The equipment upgrade will be financed by JSC "KUET," while BES will be responsible for organizing the work.
During the repair process, specialists will check the condition of the transformers, replace worn-out parts, and carry out necessary maintenance. The new transformers will help improve the quality of electricity transmission, balance the load, and ensure stable power supply for consumers.
The work will be conducted in the following districts:
- Eastern RES - 113 units under repair, 25 new;
- Western RES - 100 units under repair, 3 new;
- Northern RES - 85 units under repair, 10 new.
All of them will be fully serviced and repaired by the end of the year.