1. Description of Work:
Client: LLC "Altynken".
1.1 List of Work: The project will involve stripping and tunneling work, as well as mining preparation and mining cutting work at an altitude of 1470 meters and above, as well as below this mark (deep part). Additionally, the installation of support for underground mining workings, maintenance of these workings, assembly work in underground conditions, and the execution of other minor tasks at various horizons and sublevels are planned.
1.2 Location: The project will be implemented at the Taldybulak deposit, located in the city of Orlovka, Kemin district, Chui region, Kyrgyz Republic.
1.3 Scope and Content of Work: This work includes stripping and tunneling work, mining preparation and mining cutting work at an altitude of 1470 meters and above, as well as at depth, installation of support for underground workings, assembly and disassembly of supporting walls for backfilling work, maintenance of underground workings, as well as installation of pipelines, air ducts, and other equipment. Additionally, extraction by the method of approaches, drilling, loading, and transportation to the ore discharge, bunker, or other location as directed by the Client will be carried out.
1.4 Method of Execution: Work will be carried out with the provision of labor and materials, under a contract for a fixed comprehensive price. Major consumables, such as explosives, fuel, electricity, water supply, and ventilation, will be provided by the Client. Payment for all materials taken by the Contractor from the Client's warehouse will be deducted from interim payments based on the actual quantity received and the price for the current month (excluding explosives). Other auxiliary materials will be purchased by the Contractor.
2. Timeline for Work Completion: The project is scheduled for 365 calendar days. The planned start date is January 1, 2026, and completion is set for December 31, 2026.
3. Cost of Work: Interested organizations can contact LLC "Altynken" for consultation. After verifying the Client's qualification and technical requirements and obtaining approval, an invitation and control cost of work can be obtained.
4. Documents Required for Commercial Negotiations with the Contractor:
4.1 Financial Information:
(1) Mining license (original or certified copy) for verification.
(2) Business license (original or certified copy) for verification.
(3) Company's charter documentation.
(4) Certificate of legal entity.
(5) Power of attorney from the legal entity.
(6) Results of the work of the site director.
(7) Certificate of absence of tax arrears.
(8) Order for the appointment of the company.
(9) Achievements of the site director.
(10) Named list of key management personnel, passports, and qualification certificates.
(11) Certificate of absence of legal or arbitration disputes in recent years.
All listed documents must be submitted in Chinese and Russian languages and certified with an official seal.
4.2 Technical Information:
(1) Technical project of work.
(2) List of equipment.
This information is intended for conducting a tender for tunneling work at the Taldybulak Left Bank deposit in 2026.
The period for publishing information is from November 8 to November 20, 2025. Interested organizations must have the appropriate qualifications and work experience, and provide the necessary qualification materials and technical documentation to [email protected]. For additional information, you can contact by phone: 0701886878 and 0701886026.
Only after confirming qualifications will business negotiations be organized.