Violations Found in Land, Capital, and Project Works at the Ministry of Emergency Situations
The Audit Chamber of the Kyrgyz Republic conducted an audit, during which the results of the budget execution of the Ministry of Emergency Situations and its subordinate organizations for the years 2023–2024 were examined. As a result of the audit, numerous violations in the use of budgetary funds, as well as in project implementation and legal matters, were identified.
Auditors discovered financial violations amounting to a total of 210.8 million soms. Of this amount, 156.8 million soms are subject to return, and 66 million soms have already been returned during the audit process.
One of the serious violations was the formation and use of a separate budget for centralized events, which contradicts current legislation and budget planning rules. Moreover, allocations from this budget were subsequently approved for departmental organizations.
In the hydrometeorological service, out of 157 registered land plots, 21 plots do not have state acts. The Audit Chamber called for the acceleration of work on the registration of title documents.
Delays in the reimbursement of expenses and losses were also found in the forestry sector. For example, 96.1 million soms in rental payments for land plots did not fully reach the republican budget, indicating insufficient control in this area.
The ERIC project, aimed at increasing resilience to natural disaster risks, utilized only 13.7% of the approved budget for 2023. As a result of the early termination of the contract with the contractor, there were delays in the start of school construction.
The completion of the COVID-19 operational project was delayed by almost two years and was only finished in October 2024. At the same time, part of the funds was directed to activities unrelated to operational response; however, capital repairs of healthcare facilities contributed to the improvement of their material and technical base.
In four subordinate structures of the Ministry of Emergency Situations in 2023–2024, over 1.9 billion soms in capital investments were utilized. The audit also revealed violations amounting to 6.8 million soms.
The Audit Chamber proposed recommendations aimed at strengthening budget discipline, improving project management, and enhancing internal control within the Ministry of Emergency Situations.
Read also:
The Accounts Chamber reviewed the results of the compliance audit conducted at the Ministry of Emergency Situations.
The Accounts Chamber conducted an analysis of the budget compliance of the Ministry of Emergency...
The Audit Chamber checked the Ministry of Emergency Situations and found financial violations amounting to 210 million soms
The Audit Chamber of Kyrgyzstan conducted an audit of the budget execution of the Ministry of...
The Audit Chamber identified violations amounting to 210 million soms in the Ministry of Emergency Situations system.
In Kyrgyzstan, the Accounts Chamber conducted an audit of the budget execution of the Ministry of...
The Audit Chamber identified violations in the Ministry of Foreign Affairs amounting to 72.7 million soms
According to the press service, the Audit Chamber of the Kyrgyz Republic has completed an audit of...
The Audit Chamber identified violations in the Ministry of Foreign Affairs amounting to nearly 73 million soms
Overpayments in salaries and violations in business trips detected According to a report from the...
Violations of nearly 1 billion soms identified at the State Property Agency - audit
An audit conducted by the Accounts Chamber was carried out at the State Property Management Agency....
Violations Found in the Execution of the Budget of the State Property Management Agency in 2024
At the last meeting of the Audit Chamber of the Kyrgyz Republic, the results of the audit of the...
The Accounts Chamber revealed the misuse of a Japanese grant allocated for the purchase of agricultural machinery.
- As a result of the budget execution audit for 2024, alarming results were made public. Japan...
The Accounts Chamber identified violations amounting to 72.7 million soms in the Ministry of Foreign Affairs of Kyrgyzstan
According to the results of the audit conducted by the Accounts Chamber of the Kyrgyz Republic,...
Materials on violations in state property have been submitted to the prosecutor's office and the GKNB.
As a result of an audit conducted by the Accounts Chamber of Kyrgyzstan, numerous violations of...
Overpayments on Salaries and Transport. What Violations Were Revealed During the Audit at the Ministry of Foreign Affairs of the Kyrgyz Republic
The audit conducted by the Accounts Chamber examined the activities of the Ministry of Foreign...
As a result of the inspection, LLC "Beton Star" identified violations amounting to 103 thousand soms.
- During an unscheduled inspection conducted on November 3, the regional administration for the...
Auditors identified violations in organizations related to alcohol production
In Kyrgyzstan, the Audit Chamber conducted an audit in two institutions operating in the alcohol...
How much has the maintenance of the presidential administration cost since the beginning of the year
From the beginning of January to the end of November 2025, the expenses for the activities of the...
"Murass Synthesis" in Jalal-Abad fined 99,000 soms for environmental violations
As a result of a scheduled inspection of the activities of the LLC "Muras Synthesis" by...
In 9 months, 3755 environmental violations were identified, causing damage amounting to 102.8 million soms, - Ministry of Natural Resources
In the first half of 2025, the Ministry of Nature reported the detection of 3,755 cases of...
In Osh, the owner of the restaurant "Meerim" did not pay the city 13 million soms
According to information provided by the Osh city administration, the owner of the...
The damage from emergencies in Kyrgyzstan amounted to over 1.3 billion soms.
According to the report from the National Statistical Committee on the state of the environment in...
Expenses for the work of the Jogorku Kenesh have exceeded 1.2 billion soms since the beginning of the year
From January to November 2025, the total expenses for the activities of the Jogorku Kenesh amounted...
In 2024, 12 plots and 6 premises were returned to the ownership of Bishkek
In 2023, Bishkek received 7 billion 155.5 million soms from the rental of municipal property, which...
The Ministry of Natural Resources fined the company "Muras Synthesis" 99,000 soms for gross violations
- During a scheduled inspection conducted by employees of the Jalal-Abad Regional Office of the...
Almost 264 billion soms in Kyrgyzstan are outside the banking system
As of October 1, 2025, the total amount of money in circulation reached 290 billion 191.1 million...
Violations of Ecological Safety Identified at the "Muras Synthesis" Enterprise
The company was fined 99,000 soms A scheduled inspection of the activities of LLC "Muras...
Prosecutor General's Office: The authorized capital of "Kyrgyzstan Airports" has increased by 15.2 billion soms
The increase in the authorized capital of OJSC "Kyrgyzstan Airports" became possible...
In Talas, officials are suspected of misappropriation of funds
Employees of the State Committee for National Security (GKNB) in the Talas region discovered that...
The Ecological Supervision Service fined LLC "Beton Star" 103,000 soms for environmental violations
On November 3, employees of the Regional Department of the Ecological Supervision Service for...
The Ministry of Construction fined LLC "LAHOR STIL MILS" for illegal construction. The company must pay 800,000 soms.
The Chui Regional Department of Architectural and Construction Control conducted an unscheduled...
In Kyrgyzstan, a sharp increase in the revenues of the republican budget has been noted
According to information from the Ministry of Finance, the Republic of Kyrgyzstan is experiencing...
The Financial Supervision Authority revoked the license of LLC "Data Group" for the operation of a virtual asset exchange operator.
- The Financial Supervisory Authority of the Kyrgyz Republic has announced that the license of LLC...
A school for 750 students is being built in the Ak-Ordo residential area of the capital.
In the capital district of Ak-Ordo, the construction of a new school for 750 students has begun, as...
The Prosecutor General's Office ordered the internet platform to pay $2.885 million in taxes
In the Kyrgyz Republic, the General Prosecutor's Office has identified tax violations...
Bishkek's budget will be increased by 5.4 billion soms: 3 billion will be allocated for teachers' salaries
In Bishkek, the city administration presented a draft resolution on the adjustment of the city...
In Batken, land for the border outpost was illegally transferred to private ownership, - Military Prosecutor's Office
On November 10, the Military Prosecutor's Office announced the return of land plots to state...
Eco-safety violations identified at the enterprise "Muras Synthesis"
The scheduled inspection of the activities of LLC "Muras Synthesis" was conducted by...
The GSIN will transfer four departmental kindergartens to municipal ownership
The State Service for the Execution of Sentences (GSIN) has presented a draft resolution on the...
A school has been built in the city of Bazar-Korgon for 101 million soms
In the Jalal-Abad region, in the village of Soviet, a solemn ceremony was held to open school No....
More than 108 million soms paid by Kyrgyzgosstrakh to affected citizens
During the first ten months of 2025, the Open Joint Stock Company "State Insurance...
In the government project for agricultural financing, 6,487 loans have been issued
According to the decree of the Cabinet of Ministers of the Kyrgyz Republic, approved on February...
Markets in Uzgen fined 42,000 soms for violating sanitary standards
In Uzgen, an inspection of central markets was conducted to ensure compliance with sanitary norms...
Schools and kindergartens in Kyrgyzstan are 71 percent supplied with coal
The Ministry of Education reports that local self-government bodies are financing the expenses of...
In Shopokov, a company was fined 800,000 soms for illegal construction
Objects built without permits are subject to demolition...
In the first 10 months of 2025, the revenue of "Kumtor Gold Company" amounted to 80 billion soms
In addition to this, the company paid 16 billion 272 million soms to the budget of the Kyrgyz...
Kyrgyz National Cuisine
In the material culture of any ethnic group, there is a distinctive cuisine. It is no coincidence...