The reconstruction of the fourth hydro unit of the Toktogul HPP has been completed
At present, the testing process has already begun, aimed at extending the service life of the station and increasing its installed capacity from 1200 to 1440 megawatts. An important aspect of the modernization is the implementation of modern automated control systems.
Photo by the Ministry of Energy. Hydro Units
As part of the program for the modernization of hydroelectric facilities, the reconstruction of the second hydro unit of the Uch-Kurgan HPP has been successfully completed. Currently, tests of the new equipment are being conducted at the site.
It should be noted that the reconstruction work on the Uch-Kurgan HPP started in 2024, when the first hydro unit was replaced, which allowed for an increase in the station's capacity by 9 megawatts. Now, with the completion of the modernization of the second hydro unit, another 9 megawatts have been added.
In 2026, the reconstruction of the remaining two hydro units is planned. After the completion of all work, the total capacity of the HPP will increase by 36 megawatts, and after testing, the hydro units of the Toktogul and Uch-Kurgan HPPs will be put into operation.
In addition, Minister Ibraev got acquainted with the operation of the Kara-Kul HPP, which was recently commissioned and has a capacity of 18 megawatts. Currently, the station is operating in normal mode.
Read also:
Testing of hydroaggregates after reconstruction has begun at the Toktogul and Uch-Kurgan hydropower plants.
Talaybek Ibraev, the Minister of Energy, familiarized himself with the completion of the...
Kyrgyzstan Increases Hydropower Plant Capacity and Prepares for a Disruption-Free Winter Season
The Ministry of Energy of Kyrgyzstan held a board meeting dedicated to the results of the energy...
Uch-Kurgan Hydroelectric Power Station: Reconstruction of Unit No. 3 Completed by 98 Percent
Active work continues at the Uch-Kurgan Hydroelectric Power Station, which plays a key role in the...
The Minister of Energy inspected the construction of a solar power plant on Issyk-Kul
As part of a working trip to the Issyk-Kul region, the Minister of Energy of the Kyrgyz Republic,...
The Second Birth of Toktogul: How the Power of the Hydroelectric Station Increased to 1,440 Megawatts
Photo 24.kg. Toktogul Hydropower Plant The Toktogul Hydropower Plant, which has been supplying...
The tender for the construction of the Kara-Kechinskaya TPP has been declared unsuccessful
OJSC "Electric Stations" announced the recognition of the tender for the EPC contract for...
Minister of Energy Ibraev: Most of Atambayev's Statements Are Pure Lies
Energy Minister Talaybek Ibraev responded to recent statements made by Almazbek Atambayev...
Uch-Kurgan Reservoir
Uch-Kurgan Hydroelectric Power Station — a hydraulic engineering structure, a run-of-river...
Daiyrbek Orunbekov explained the reasons for power outages in Kyrgyzstan
Daiyrbek Orunbekov, head of the president's information policy service, commented on the...
Sadyr Japarov urges not to complain about power outages: Endure for another 2.5 years
Addressing the people on October 27 during his working trip to the Jalal-Abad region, Zaparov...
Kambaratin Hydroelectric Power Plant-2: Ongoing Major Repairs of Unit No. 1 and Site Improvement
Currently, the following works are being carried out at the station: • major repair of hydro unit...
In Kyrgyzstan, one of the hydro units of the Toktogul HPP has been put back into operation.
The energy crisis and rolling blackouts in Kyrgyzstan this winter are no longer a threat. One of...
The Minister of Health Familiarized Himself with the "Arashan" Central Outpatient Clinic
On October 25, Minister of Health Erkin Checheybaev made a working trip to the "Arashan"...
The Minister of Energy inspected the progress of construction of the Orto-Tokoy Hydroelectric Power Station
During a working visit to the Issyk-Kul region, the Minister of Energy of the Kyrgyz Republic,...
API error: HTTP 429
API error: HTTP 429...
In nine months, 2.7 billion kWh of electricity was imported into Kyrgyzstan
AppleMark According to data obtained at the end of the first nine months of 2025, the total...
Reconstruction of the Aravan-Ak-Buurinsky Canal has begun in the Osh Region
- During his working trip to the Osh region, the Minister of Water Resources, Agriculture, and...
A new substation has been put into operation in the city of Osh
A new substation "Kең-Sai" was opened in Osh on October 30. Attending the event were the...
All mining farms in Kyrgyzstan have been shut down — Talaybek Ibraev
Photo of the Cabinet of Ministers of the Kyrgyz Republic. Talaybek Ibraev The Minister of Energy...
Orunbekov: Energy deficit is a temporary phenomenon, the country is building dozens of new hydropower plants
The country continues to actively implement a large-scale program to increase energy capacity...
President Sadyr Japarov inaugurated the "Kara-Kul" Hydroelectric Power Station worth $25 million
The hydroelectric power station is located in the lower reaches of the Kara-Suu River, where it...
The Minister of Energy urges café owners to save on outdoor lighting
The Minister of Energy, Talaybek Ibraev, appealed to café owners to save electricity, especially...
The minister commented on Sadyr Japarov's request not to complain about power outages in winter.
In an interview on "Birinchi Radio," Minister Ibraev pointed out the need for openness...
Sadyr Japarov was surprised when the speaker of the city council requested 300 million soms for the reconstruction of facilities.
The speaker of the Kara-Kul City Council, Chyngyz Kimsanov, addressed President Sadyr Japarov with...
Development of Renewable Energy Sources in Kyrgyzstan: Proposed to Increase Project Capacity to 50 MW
The Ministry of Energy of the Kyrgyz Republic has presented a draft law concerning amendments to...
President Zaparov familiarized himself with the condition of kindergarten No. 11 in Karakol after renovation.
On November 1, President Sadyr Japarov visited kindergarten No. 11 in Karakol during his working...
ADB to Support Mongolia in Landmark Solar Energy and Energy Storage Project
In its official statement, the ADB specified that the creation of facilities with a capacity of...
A new 110/10 kV substation "Ken-Sai" has been put into operation in Osh
The opening of the 110/10 kV substation "Ken-Sai" took place in Osh, which will ensure...
By the end of November, the rehabilitation of GES No. 3 of the Toktogul Hydroelectric Power Station will be completed.
A meeting of the board organized by the Ministry of Energy of the Kyrgyz Republic took place in...
Tender announced for the construction of the power transmission line "Tamga - Karakol" – Ibraev
A tender for the construction of the power transmission line "Tamga - Karakol," which...
Sadyr Japarov: Use Light Economically
President of Kyrgyzstan Sadyr Japarov once again addressed the public with a call to carefully...
The Minister of Energy accused Atambayev of manipulating facts about energy.
In a recent social media post, former president Almazbek Atambayev reminded about the start of...
Sadyr Japarov explained the situation in the country's energy sector
The President urged citizens to use electricity sparingly Sadyr Japarov, the President of...
The President ordered to start the construction of mortgage houses in the city of Kara-Kul
On October 27, 2025, President Sadyr Japarov announced the start of construction of mortgage houses...
Agreement with China: A 250 Megawatt Solar Power Plant Will Be Built in Kyrgyzstan
At the international forum taking place in Suzhou, the Ministry of Energy of the Kyrgyz Republic...
Energy on the Path to Self-Sufficiency: Sadyr Japarov's Message to the People
President Sadyr Japarov addressed the people of Kyrgyzstan to discuss the current situation in the...
In the village of Mangyt in the Aravan district, a school for 550 students has been renovated.
In the village of Mangyt, located in the Aravan district of the Osh region, the major renovation of...
In Kochkor, the "Seil" Park will be reconstructed. Sketches
In the village of Kochkor, the reconstruction of the "Seiyil" park is planned, as...
The 110/10 kV Substation "Ken-Sai" Put into Operation in Osh
According to the Ministry of Energy of Kyrgyzstan, the new substation "Ken-Sai" will...
Kamchybek Tashiev was shown the reconstructed wastewater treatment station costing 5.5 million euros.
Today, October 30, the ceremonial commissioning of the upgraded wastewater treatment station No. 2,...
The Minister of Energy inspected the progress of the solar power plant construction in the Issyk-Kul region
Curl error: Could not resolve host: api.openai.com...
The Minister of Natural Resources visited the Jalal-Abad Regional Office of the Department
During his visit to the Jalal-Abad region, the Minister of Natural Resources, Ecology, and...