The new "Azattyk Arena" stadium in Bishkek will be ready by August 1, 2026.

Яна Орехова Local news
VK X OK WhatsApp Telegram
Kanibek Tumanbaev, the head of the president's administration, visited the construction site of the new "Azattyk Arena" stadium in Bishkek. During the visit, he reviewed the progress of the work and checked its quality, the press service of the agency reports.

According to Tumanbaev, the pace of construction is satisfactory and is proceeding according to the established schedule. Currently, 80% of the concrete work has been completed, and the remaining portion is planned to be finished by December 10. After that, the installation of structures will begin, which is expected to be completed by February 15.

He also noted that work on laying engineering networks, finishing, and creating internal and external infrastructure is simultaneously underway at the stadium. All key tasks are being carried out synchronously and without delays.

Tumanbaev highlighted the uniqueness of the stadium project, which includes 40,000 square meters of retail space for international brands. This format is not typical for most foreign arenas.

At the end of his working trip, he confirmed that the new "Azattyk Arena" stadium will be fully ready by August 1, 2026.