Hundreds of workers and units of machinery have been involved in the large-scale construction
In the area of the Northern Bypass road, located near Bishkek, reconstruction work is actively underway, as reported by the Ministry of Transport of the Kyrgyz Republic.
The aim of this work is to increase the road's capacity and improve traffic flow. As part of the project, the roadway will be expanded to six lanes, each of which will be 3.75 meters wide.
A large number of resources are involved in the project: over 500 specialists and 240 units of machinery are working around the clock.
Engineers have already completed several key stages, including the installation of span slabs on the bridge over the Nooruz River and the installation of supports across the canal.