Preparation for the launch of the second hydro unit of the Kambar-Ata HPP-2. What has already been done

Наталья Маркова Economy
VK X OK WhatsApp Telegram
The press service of JSC "Electric Stations" reported on the ongoing process of commissioning the second hydro unit of the Kambar-Ata HPP-2.

The project is being implemented with the financial support of the Eurasian Stabilization and Development Fund, while the international consulting company Fichtner GmbH & Co. KG provides technical support and supervision.

The work is divided into three lots, for which contractors were selected based on the results of international tenders:

Current Progress




Photo by the press service of JSC "Electric Stations".



Photo by the press service of JSC "Electric Stations".



Photo by the press service of JSC "Electric Stations".



Photo by the press service of JSC "Electric Stations".



Photo by the press service of JSC "Electric Stations".



Photo by the press service of JSC "Electric Stations".

As part of the project, the following important works have already been completed:

JSC "Electric Stations" maintains constant control over the implementation of the project together with contractors and engineering consultants to ensure that all work is carried out according to established schedules, as noted in the statement.