This project is referred to as the "project of the century." Currently, the installation of power lines is actively underway, along with construction work on the shift camp, bridges, and roads.












What has already been done:
- The road from the 318 km mark of the Bishkek - Osh highway to cut No. 2 (length 8.6 km) has been completed and is in the acceptance stage;
- The road from cut No. 2 to the HPP-1 site (4.7 km) - about 4 km has been completed (approximately 95%);
- The transport tunnel TT-2 (126 m) - drilling and concrete works have been completed 100%, the facility is undergoing acceptance;
- The 110 kV power line and 110/6 kV substation - 11.5 km of line has been laid, 25 supports installed, major works at the substation are 90% complete;
- The shift camp for 100 people (including an administrative building, dormitory, and cafeteria) - construction works are 60-70% complete;
- The bridge over the Naryn River to the right bank of the HPP-1 site - the concreting of four supports has been completed, the installation of metal structures for the spans is ongoing (the length of the bridge is over 180 m, readiness 50-60%);
- The concrete road in the transport tunnel TT-2 (1,387 m) - fully completed, internal structural works are ongoing (overall readiness 55-60%).