The capacity of 5 substations has been increased in Bishkek
In 2025, modernization was carried out in Bishkek, resulting in a significant increase in the capacity of five substations located in densely populated areas.
The specific changes are as follows:
- Substation 110/10 kV "Kok-Zhar" — transformer replaced from 25 MVA to 40 MVA;
- Substation 110/10 kV "Orto-Alysh" — also replaced transformer from 25 MVA to 40 MVA;
- Substation 110/10 kV "Altyn-Kazyk" — transformer capacity increased from 16 MVA to 25 MVA;
- Substation 110/10 kV "Berlik" — similarly, from 16 MVA to 25 MVA;
- Substation 110/10 kV "Vodokanal" — transformer with a capacity of 6.3 MVA replaced with 16 MVA;
Thus, the total increase in capacity at all five substations amounted to 146 MVA, which will allow residents of the city to be provided with quality electricity. Additionally, by the end of the current year, it is planned to increase the capacity of two more substations.
These modernization works are being carried out as part of an agreement between the Ministry of Energy and the World Bank.
"The main goal of these activities is to successfully pass the autumn-winter season, as well as to ensure reliable power supply for the capital's population and improve service quality," the official statement says.
Read also:
Ministry of Energy of Kyrgyzstan: The capacity of 5 substations has been increased in Bishkek
Among the substations that have undergone modernization are: — PS 110/10 kV "Kök-Jar" –...
The capacity of five substations in Bishkek has been increased
In Bishkek, the modernization of five substations located in densely populated areas has been...
Master Plan 2050. The number of ambulance stations in Bishkek is planned to triple.
According to the draft general plan for Bishkek until 2050, it is proposed to significantly...
Kyrgyzstan Increases Hydropower Plant Capacity and Prepares for a Disruption-Free Winter Season
The Ministry of Energy of Kyrgyzstan held a board meeting dedicated to the results of the energy...
In nine months, 2.7 billion kWh of electricity was imported into Kyrgyzstan
AppleMark According to data obtained at the end of the first nine months of 2025, the total...
How NESK Assesses the Readiness of Kyrgyzstan's Energy System for the Autumn-Winter Period
Isabek Orozbaev, a representative of NESK, stated in an interview on "Birinchi Radio"...
Development of Renewable Energy Sources in Kyrgyzstan: Proposed to Increase Project Capacity to 50 MW
The Ministry of Energy of the Kyrgyz Republic has presented a draft law concerning amendments to...
The reconstruction of the Toktogul and Uch-Kurgan hydropower units has been completed.
The reconstruction of the fourth hydroaggregate of the Toktogul HPP and the second hydroaggregate...
The Issyk-Kul Electric Network Enterprise has completed preparations for the heating season.
The Issyk-Kul Electric Networks Enterprise has successfully completed the preparatory activities...
The reconstruction of the fourth hydro unit of the Toktogul HPP has been fully completed.
The Minister of Energy became acquainted with the reconstruction of the fourth hydro unit of the...
Bishkek Master Plan: By 2050, the capital will have 37 hospitals and 65 clinics
By 2050, it is planned to establish about 37 stationary medical institutions in Bishkek with a...
The reconstruction of the fourth hydro unit of the Toktogul HPP has been completed
During his working trip to the Jalal-Abad region, the Minister of Energy of the Kyrgyz Republic,...
API error: HTTP 429
API error: HTTP 429...
The tender for the construction of the Kara-Kechinskaya TPP has been declared unsuccessful
OJSC "Electric Stations" announced the recognition of the tender for the EPC contract for...
Energy workers explained how Kyrgyzstan residents can avoid automatic disconnection of meters.
To reduce the load, for example, it is enough to turn off the electric stove, which will allow...
NESC introduces power restrictions in case of substation overloads
The National Electric Network of Kyrgyzstan (NESC) has announced the introduction of temporary...
Energy consumption in Kyrgyzstan reached 13.8 billion kWh
Today, a meeting of the Ministry of Energy took place in Bishkek, where the results of the energy...
Tash-Kumyr Electric Network Completes Preparation for the Autumn-Winter Period: New Power Lines Built
The Tash-Kumyr Electric Networks (RES) is completing preparatory activities for the autumn-winter...
Ministry of Energy: Issyk-Kul PES has completed preparations for the autumn-winter period of 2025–2026
The Ministry of Energy of Kyrgyzstan has announced the completion of preparatory work at the...
Damage to Kyrgyzstan's Nature: Nearly 103 Million Som for Nine Months of 2025
According to information provided by the Ministry of Natural Resources, Ecology, and Technical...
A Small Hydroelectric Power Plant Launched in Kadamzhai
In the Kadamjay district, in the rural municipality of Maidan, the construction of the small...
The Minister of Energy instructed to ensure round-the-clock delivery of coal to the population
During a visit to the branch of OJSC "Kyrgyzkomur" in Balakchy, Minister of Energy...
Uch-Kurgan Hydroelectric Power Station: Reconstruction of Unit No. 3 Completed by 98 Percent
Active work continues at the Uch-Kurgan Hydroelectric Power Station, which plays a key role in the...
The Minister of Energy inspected the progress of construction of the Orto-Tokoy Hydroelectric Power Station
During a working visit to the Issyk-Kul region, the Minister of Energy of the Kyrgyz Republic,...
ORT for winter university admissions will take place from November 21 to 23.
The winter nationwide testing for university admission is scheduled for November 21-23. The testing...
General Plan Forecasts: By 2050, Bishkek will have a population of 2 million people
According to new data from the General Plan for 2025-2050, Bishkek is expected to see its...
Master Plan 2050: Schools and Kindergartens in Bishkek Promised to Become More Accessible
As part of the general plan for the development of the capital until 2050, improvements in the...
The Minister of Energy accused Atambayev of manipulating facts about energy.
In a recent social media post, former president Almazbek Atambayev reminded about the start of...
In Bishkek, an analytical review titled "Aging Population of the Kyrgyz Republic: Challenges and Prospects" was presented.
On October 31, an analytical report titled "Aging Population of Kyrgyzstan: Challenges and...
In the city of Osh, private mansions have been ordered to be disconnected from central heating.
In Osh, on October 28, the modernized boiler house "Kermе-Too" was ceremoniously opened....
Orunbekov: Energy deficit is a temporary phenomenon, the country is building dozens of new hydropower plants
The country continues to actively implement a large-scale program to increase energy capacity...
A Huge Wind Turbine is Being Built in Bishkek
This installation significantly exceeds the size of the one located at Issyk-Kul Work is underway...
Consumption Power Limitations for the Population - NESC Comment
The company emphasized that this is a temporary measure OAO "National Electric Network of...
"Unlimited tariff increases the gap between the rich and the poor"
An expert opposes this approach in the context of electricity shortages At the National Electric...
The 110/10 kV Substation "Ken-Sai" Put into Operation in Osh
According to the Ministry of Energy of Kyrgyzstan, the new substation "Ken-Sai" will...
In Kyrgyzstan, the power of electricity meters will be temporarily limited during peak hours
According to OJSC "National Electric Network of Kyrgyzstan" (NESC), from 07:00 to 09:00...
The city hall has begun the demolition of over 1,000 garages on Repina and P. Lumumba Streets.
The process of dismantling more than 1,000 garages located on municipal land has been initiated by...
In the Chui Region, the water supply system is being modernized
In the Tort-Kul rural district of the Moscow region in Chui Province, a large-scale modernization...
Master Plan 2050. Bishkek Plans to Increase Average Housing Provision
In Bishkek, an increase in the average level of housing provision is planned. This is stated in the...
What does the Botanical Garden in Bishkek look like during reconstruction? Photo report
Since April 2025, active repair and restoration work has been underway at the Botanical Garden...
As part of the land amnesty, data is being clarified on-site
In Bishkek, an active verification of information regarding land plots that fall under the...
Exchange rates in commercial banks on November 10
As of November 10 of this year, the exchange rates for foreign currency set by the National Bank of...