- In the spring, the commissioning of the second hydro unit at the Kambar-Atynska HPP-2 will begin. This stage is part of the ministry's program aimed at the phased increase of generating capacities.
- At the same time, the reconstruction of two hydro units at the Uch-Kurgan HPP is planned. Work on unit No. 2 will start in February, followed by the reconstruction of unit No. 1 in March. This will allow for the effective updating of the station's equipment.
- Construction and infrastructure activities continue at the Kambar-Atynska HPP-1. Finishing works are underway in the administrative and domestic complex, while engineering communications, including the installation of sewage and water supply systems, as well as the installation of internal partitions, are being completed in the under-construction dormitory.
- At the Kurpsai HPP, work has begun on the replacement of two autotransformers (AT-1 and AT-2) in the 220 kV switchgear section to increase capacity. The first autotransformer was delivered in January 2026, and the second is expected in March. Installation is planned to start on April 1, 2026, with completion scheduled for the fall. This will significantly enhance the operational capabilities of the station.
- A new administrative building has been constructed for the employees of OJSC "Electric Stations," meeting modern requirements. It provides all the conditions for productive work. In this regard, phased renovations in the administrative buildings of the company's branches are planned for 2026.
How they plan to develop hydropower. Data from the Ministry of Energy
Read also:
The comprehensive modernization of the hydropower cascade in Kyrgyzstan continues
The Ministry of Energy of Kyrgyzstan is actively working on a number of projects aimed at...
Testing of hydroaggregates after reconstruction has begun at the Toktogul and Uch-Kurgan hydropower plants.
Talaybek Ibraev, the Minister of Energy, familiarized himself with the completion of the...
Ibraev proposed to the Chinese to invest in the construction of the power lines "Kemin-Torugart" and "Barskoon-Bedel"
Curl error: Operation timed out after 120001 milliseconds with 0 bytes received...
At one hydroelectric power station, a parallel reconstruction of two hydro units will be carried out.
As part of the modernization project for the Uch-Kurgan hydroelectric power station, a parallel...
The capacity of the Uch-Kurgan Hydroelectric Power Station will increase by 36 MW by the end of 2026.
In 2026, it is planned to modernize two hydro units — No. 1 and No. 2 at the Uch-Kurgan HPP....
Launched updated hydro units of Toktogul and Uch-Kurgan hydropower plants
In the Jalal-Abad region, the Minister of Energy of Kyrgyzstan, Talaybek Ibraev, conducted a...
The reconstruction of the Toktogul and Uch-Kurgan hydropower units has been completed.
The reconstruction of the fourth hydroaggregate of the Toktogul HPP and the second hydroaggregate...
The exhibition "Kyrgyzstan EXPO 2025" started today in Bishkek.
Curl error: Operation timed out after 120001 milliseconds with 0 bytes received...
Preparation for the launch of the second hydro unit of the Kambar-Ata HPP-2. What has already been done
The press service of JSC "Electric Stations" reported on the ongoing process of...
Kyrgyzstan Agreed to Build a Cascade of Small Hydropower Plants on One River for $300 Million
On January 23, the Cabinet of Ministers of the Kyrgyz Republic signed a memorandum with LLC...
Ministry of Energy: Construction of the Orto-Tokoy Hydroelectric Power Station is nearing completion
According to the press service of the Ministry of Energy, OJSC "Chakan HPP" has already...
By the end of 2026, two hydro units of the Uch-Kurgan HPP will be upgraded
It is expected that the upgrade of two hydro units at the Uch-Kurgan HPP will be completed by the...
Taalaybek Ibraev: All mining farms in Kyrgyzstan have been shut down
In an interview with 24.kg, Talaybek Ibraev reported a critically low water level in the Toktogul...
Results of 2025 in Energy: Tariff Increases, Power Outages, and Plans for Kambar-Ata-1
In 2025, Kyrgyzstan faced a problem of insufficient energy capacity and engaged in active...
Main Hydroelectric Power Stations of Kyrgyzstan: When and How They Were Built and How Old They Are Now
The total potential of Kyrgyzstan's energy resources is 245.2 billion kWh, of which only 142.5...
Bakyt Torobaev familiarized himself with the activities of the Potato Farming Development Center "Tyup"
On November 24, 2025, the Minister of Water Resources, Agriculture, and Processing Industry, Bakyt...
Prices are rising, demand is falling: what is happening with the real estate market in Bishkek
In 2025, Bishkek is experiencing a significant rise in housing prices — both for apartments and...
The Roads of Independent Kyrgyzstan: Major Infrastructure Projects Funded by the State Budget
In recent years, there has been active development of road infrastructure in Kyrgyzstan, funded by...
Products of Batken gardeners enter new markets thanks to a new enterprise
In the Batken region, in the village of Samarkandek, a new enterprise has opened that processes...
In Bishkek, the best exporters of the country were awarded
On December 24, 2025, the final of the national competition "Best Exporter of the Kyrgyz...
Kyrgyzstan and China Discussed the Implementation of Projects for the Kambar-Ata and Uch-Kurgan Hydroelectric Power Stations
Alibek Sadyrov, head of JSC "Electric Stations," participated in events organized by...
Bishkek Became the Venue for the B5+1 Business Forum – Photo Report
The B5+1 business forum has started in Bishkek, which will last for two days. This event has...
Torobaev: Over the past five years, electricity consumption in the Kyrgyz Republic has increased by 25%
During the meeting of the collegium of the Ministry of Energy, dedicated to the results of work...
In the capital, the pilot delivery of solid waste to the new waste processing plant has begun
In the capital, the first stage of the delivery of solid household waste (SHW) to the new waste...
The Russian-Kyrgyz Development Fund invested $1 billion in the economy of Kyrgyzstan
For a successful business start, financial assistance is essential. The Russian-Kyrgyz Development...
Kyrgyzstan will increase cargo transportation volume to 110 million tons by 2030 — Sydykov
Currently, the second day of the Central Asian Regional Economic Cooperation (CAREC) business...
Finland taught artificial intelligence data centers to heat cities
In 2026, Google and Microsoft are launching unique projects in Finland, where the waste heat from...
"Rosatom to Implement 3D Printing in Kyrgyzstan's Hydropower Sector"
An important agreement regarding the implementation of additive technologies in the renewable...
The Second Birth of Toktogul: How the Power of the Hydroelectric Station Increased to 1,440 Megawatts
Photo 24.kg. Toktogul Hydropower Plant The Toktogul Hydropower Plant, which has been supplying...
Modern reclamation technologies are being implemented in the Chui region to restore arable land
As part of his working trip, the Minister of Water Resources, Agriculture, and Processing...
The project of a cascade of small hydropower plants on the Tar River is estimated at $300 million
On January 23, 2026, a memorandum of understanding was signed between the Cabinet of Ministers and...
The power of the Uch-Kurgan Hydroelectric Power Station has increased
The major repair and modernization of the second hydro unit of the Uch-Kurgan HPP has been...
How Farmers in the Chui Region Use Preferential Loans – Inspection by the Ministry of Agriculture
On January 15, 2026, the Deputy Minister of Water Resources, Agriculture, and Processing Industry...
At the GNS, issues of export and re-export were discussed
Kubanychbek Isabekov, Deputy Chairman of the State Tax Service under the Government of the Kyrgyz...
Kyrgyzstan Presented Key Directions of the "B5+1" Forum to the Diplomatic Corps
Today, a joint briefing organized by the Ministry of Foreign Affairs and the Ministry of Economy...
At the GNS, issues of cashless payments for businesses were discussed
The State Tax Service (GNS) held a meeting dedicated to issues related to the application of...
A new high-voltage substation "Suu-Bashi" has been put into operation in Batken
Photo by the Ministry of Energy. Substation 'Suu-Bashi' A new high-voltage substation...
Kyrgyzstanis Mainly Work Informally. What Reforms Could Change the Situation?
In 2025, an analytical report by the International Monetary Fund was presented, dedicated to the...
In Kyrgyzstan, the fourth hydro unit of the Toktogul HPP has been put into operation
Photo 24.kg. Machine hall of the Toktogul HPP The press service of the Ministry of Energy of...
The fourth hydro unit has been launched at the Toktogul HPP after reconstruction.
A project for the construction of floating solar power plants is planned at the Toktogul Reservoir....
Yusuf (Jusup) al-Balāsaghūnī
Yusuf (Jusup) al-Balасaguni was born around 1015-1018 in the principality's capital, which...